PBVUSD - Earl Warren JHS Modernization
Status
Bidding Closed
Prebid Date | 3/4/25 9:00am |
Bid Date | 3/25/25 2:00pm |
Company & Contacts
INTRODUCTION
Panama-Buena Vista Union School District is inviting suppliers and subcontractors to submit bid proposals for the Earl Warren Junior High School Modernization project. The project is located at 4615 Mountain vista Drive, Bakersfield, CA.
DESCRIPTION OF WORK
This project consists of a modernization per the DSA-approved plans and specifications dated 7/20/23.
This is a Multiple Prime contract bid to Panama-Buena Vista Union School District, MWC is the Construction Manager. Plans, specs, and all Addenda must be reviewed and incorporated into each bid. The following are the bid packages associated with this project:
WJH - 01 DEMOLITION/ABATEMENT: C-21 or C-22 License Requirement
WJH - 02 SITE/BUILDING CONCRETE: A, C-8, B License Requirement
WJH - 03 DELETED 2/21/25 – (SEE WJH-04)
WJH - 04 GENERAL SPECIALTIES: B License Requirement
WJH - 05 PAINTING (REVISED 2/21/25): C-33 License Requirement
WJH - 06 PLUMBING/SITE UTILITIES: C–36 License Requirement
WJH - 07 MECHANICAL: C–20 License Requirement
WJH - 08 ELECTRICAL/LOW VOLTAGE: C–10 License Requirement
WJH - 09 LANDSCAPE/IRRIGATION: C–27 License Requirement
All bids need to include all proper bid docs as called out in the Notice to Contractors & Instructions to Bidders.
Mandatory Pre Bid Meeting
To be eligible to bid this project, all bid packages must attend one of the Mandatory Job Walks.
First Meeting:
Tuesday, March 4th, at 9:00 am at Earl Warren Junior High School, 4615 Mountain Vista Drive, Bakersfield, CA (Administration Building).
Second meeting:
Thursday, March 6th, at 9:00 am at Earl Warren Junior High School, 4615 Mountain Vista Drive, Bakersfield, CA (Administration Building).
This project is subject to Pre-Qualification pursuant to AB 1565 of all general contractors and all mechanical, electrical and plumbing subcontractors. If required, a Prequalification package may be obtained by downloading the necessary forms from https://www.pbvusd.k12.ca.us/departments/business-services/facilites-planning-construction/vendor-information. A bid package will not be accepted from any bidder that is required to submit a completed questionnaire and supporting documents pursuant to AB 1565, but has not done so at least ten (10) business days prior to the date fixed for the public opening of sealed bids or that has not been prequalified for at least five (5) business days prior to that date.
DURATION OF WORK
Time to Complete: 127 Calendar Days
Wage Scale: Prevailing Wage
Delivery Method: CM-Multi Prime
Liquidated Damages: $500/day
Minority Goals: DVBE
DIR Register: Yes